Tower T1 – T19

Tower T1 – T19

Completed. Currently Key handover

for fitments going on. Ready with club house, temple and parking.

Tower 20

Tower 20

Construction in Tower 20 has achieved substantial progress, with major core and finishing activities completed.

Work Completed:

  • Plumbing & waterproofing works
  • Main door frames & balcony railings
  • Flooring in flats & common areas
  • Exterior painting at entrance elevation

Work in Progress:

  • Internal door frames
  • Putty works (first coat)
  • Aluminium windows & doors
Tower 21

Tower 21

Tower 21 is progressing well, with structural and finishing works moving forward in parallel.

Work Completed:

  • Waterproofing works
  • Main door frames
  • Flooring works including stairs

Work in Progress:

  • Plumbing works
  • Internal door frames
  • Putty works
  • Balcony railings
Tower 22

Tower 22

Construction activities in Tower 22 are advancing, with multiple finishing trades actively underway.

Work Completed:

  • Waterproofing works
  • Balcony railings

Work in Progress:

  • Plumbing works
  • Flooring works
  • Putty works
Tower 23

Tower 23

Tower 23 is currently under active development, with focused efforts on civil and allied works.

Work Completed:

  • Balcony railings

Work in Progress:

  • Plumbing works
  • Waterproofing works
🏠